Abnormally Low Tender Explanation (Turkey)

In Turkish public procurement a bid below the threshold value is not rejected outright — the authority asks the bidder to explain it. The explanation is a technical file with a short deadline: for construction works at least five working days (Communiqué art. 45.1.2). Every queried item needs an analysis, every analysis input needs a source, every source needs a document. Wherever that chain breaks, the bid is rejected.

We build that file from the query letter to an EKAP-ready set. Send the letter and get scope and timing the same day: free scope review.

The first 24 hours

The query letter says two things: which work items are queried and which analysis inputs need no explanation. Misreading either weakens the file from the start.

  • Scope: the authority selects the items that make up 80% of its estimated

cost from a ranked list; only those are queried (art. 45.1.2.1). An analysis for an unqueried item adds pages, not strength.

  • Exempt inputs: inputs at or below 3% of the analysis total are listed in

the letter. They still appear in the analysis, but no document is required. Labour is never exempt (art. 45.1.2.2).

  • Analysis format: the format issued with the tender documents or attached to

the letter is binding (art. 45.1.4). A correct analysis in your own format fails on procedure.

  • Deadline: it is the e-signed upload time on EKAP, not the moment the file

is finished.

What the defence file contains

  • Summary of queried items — item number, description, quantity, bid unit

price and amount; the total matches the bid schedule to the kuruş.

  • Unit-price analyses — one per queried item, in the authority's format,

with contractor profit and overhead of at least 10% on the input total (art. 45.1.3).

  • Public rate list — for items explained with official unit prices:

institution and item code, for the month of the tender notice (art. 45.1.5).

  • Third-party price quotations (proforma) — for special items and market

purchases, supported by cost / sales-value inspection minutes certified by a licensed accountant (Annexes O-5, O-6, O-7) and the stock inspection minute (Annex O-8).

  • Transport calculations — using the distances stated in the query letter;

formula and coefficient consistent with the analyses.

  • Technical statement — construction method, equipment and site-specific

conditions; answers only the questions asked.

  • Index of annexes — one page showing which document closes which item and

which input. The evaluation committee reads the file from here.

Delivered as a numbered PDF set, ready for EKAP upload.

Five working days, step by step

Day Work Output
0Read the query letter; list queried items and exempt inputsScope table (free)
1–2Quantities and analyses; separate items covered by public unit pricesAnalysis set, rate list
2–3Collect proformas, get inspection minutes certified, transport calculationsO-5/O-6/O-7/O-8, transport schedule
4Cross-check analysis ↔ summary ↔ bid schedule; period and rounding auditCheck report
5Technical statement, index of annexes, PDF setEKAP-ready file

Why files are rejected

Mostly documents and procedure, not arithmetic. The headings that recur in Public Procurement Authority decisions:

  1. Rates from the wrong month — one item at March prices, another at July;

a price outside the notice month loses the art. 45.1.5 shortcut.

  1. Proforma without minutes or signatures — a price quotation alone is not

evidence.

  1. Analysis without profit — below the 10% floor.
  2. Wrong format — the authority's analysis format ignored.
  3. Internal inconsistency — kuruş differences between analysis, summary and

bid schedule; the committee corrects them ex officio, and if the corrected figure exceeds the bid price the bid is rejected (art. 45.1.3).

  1. Scope errors — explaining an unqueried item, or skipping a queried one.

In our own archive of 37 defence files from 2012–2014, 15 of the 26 rejected files were rejected for a proforma-invoice reason: a photocopy, a missing brand or specification, or a proforma standing alone with nothing to corroborate it.

How the response is structured

There is no template letter that works; the file follows the authority's item list and analysis format. The order the committee expects:

  1. Cover letter — tender registration number, date and reference of the

query letter, items explained, list of annexes.

  1. Summary of queried items — total equals the bid schedule.
  2. Analyses — in item order, authority's format, profit line visible.
  3. Source index — for each input: public rate (institution + code),

proforma (minute number) or own production record.

  1. Documents — proformas, O-5/O-6/O-7/O-8 minutes, rate-list pages,

distance letter.

  1. Technical statement — method, equipment, site conditions.

Why it is different with us

Files are not written one by one; they are produced with our own ADS Generator software, backed by a period-tagged price memory of 308,013 rate lines and 269,301 subcontractor records from forty-five sources (April 2024 – June 2026). In practice: which month's rate supports which item is never in doubt, and the source is shown line by line.

If it is rejected

The route continues with a complaint to the authority and an objection to the Public Procurement Authority. The filing fee depends on the estimated-cost band (64,652 – 258,810 TL in 2026); we tell you before you pay it whether the file can win.

362Recorded projects
360Recorded work

Frequently asked questions

How long do we have to submit the explanation?
For construction works the contracting authority must allow at least five working days (Public Procurement General Communiqué, art. 45.1.2); for service procurements at least three (art. 79.2.1). The exact deadline is in the authority's letter — send it to us the day it arrives.
Which items have to be explained?
Only the work items that make up 80% of the authority's estimated cost, taken from its ranked list (art. 45.1.2.1). Within each analysis, inputs at or below 3% of the analysis total are exempt — except labour, which is never exempt (art. 45.1.2.2).
Is profit mandatory in the analyses?
Yes. Each analysis must show contractor profit and overhead of at least 10% on top of the input total (art. 45.1.3). A file without that line is the easiest one to reject.
Can we use official unit prices instead of analyses?
If you bid the published public unit price for the month of the tender notice, or higher, a list naming the institution and item code is enough; no analysis is required (art. 45.1.5). A price from another month loses that shortcut.
Who uploads the file to EKAP?
We deliver the file ready to upload; the e-signature and the upload stay with you. We never enter the system on your behalf.
What do you need from us to start?
The authority's query letter, your unit-price bid schedule, the analysis format given in the tender documents, and any proforma or analysis inputs you already have. The scope review is free and done the same day.
How do you charge?
A modest upfront fee, then a success fee tied to winning the contract. We share the risk.
What if the explanation is rejected?
A complaint to the authority and then an objection to the Public Procurement Authority (KİK) are available. We prepare the technical file and the precedent review, and tell you before you pay the filing fee whether the file can win.

Request a free preliminary review

Send us your project

We do not quote without seeing the scope. Send your documents; we review them free of charge and set the scope and the price with you.

Upload your documents · free review 15-min call on WhatsApp