The measurement record is where work turns into a number. Work that was never measured and drawn on site cannot be defended in the final account — there is no document left behind the payment line.
Measurement records are usually produced inside an interim payment or final account file; here they are taken on their own — we deliver the measurement, the drawings and the as-built set, and you run the account. For the full file: Interim payments · Final accounts.
Scope
- Measurement record drawings — a detailed drawing for each work item, checked, with quantities taken from it.
- On-site measurement — precise laser measurement at the place of work.
- Panoramic photography — a visual record of the work as built.
- As-built — preparation of end-of-works drawings.
- Surveys — branch surveys and concept architectural drawings.
Where we have done it
Sinpaş Ankara Güneypark (blocks A-F-O and 45C–48C), Tuzla MESA Blocks (C-D-F-G), DeFacto retail branches and bank concept branches.
What is different